      All,Ā 

      Our current practice when setting up routes is to change the run time to show 1 hour of work, and then how ever many widgets can be produced in that hour for process qty.Ā  How does the accuracy change if you put how many hours it takes to run 1 widget?Ā  Is it just preference or is there a reason why we have been taught this way?Ā  Ā Our AX was implemented way before my time.

      ——————————
      Jessica Murphy
      Master Planner
      Goodwill Industries of Central Indiana
      AX2009 Operations & Maintenance SIG Leader
      Indianapolis IN
      ——————————

    • Robert Stogner

      Member

      November 10, 2017 at 8:20 AM

      It can be done either way.Ā  If you build a large machine and it takes several hours to build 1, then you should do it that way, but most companies can build multiple units of a product in one hour (or even sometimes one minute).Ā  It just becomes a matter of decimal accuracy.Ā  I have companies that change the Hours/Time to .0167 because they put it units (for instance feet) per minute which this would reflect.

      ——————————
      Robert Stogner

      ——————————
      ——————————————-

    DSC Communities replied 7 years, 10 months ago 1 Member · 0 Replies
  • 0 Replies

Sorry, there were no replies found.

The discussion ‘Routes’ is closed to new replies.

Start of Discussion
0 of 0 replies June 2018
Now

Welcome to our new site!

Here you will find a wealth of information created for peopleĀ  that are on a mission to redefine business models with cloud techinologies, AI, automation, low code / no code applications, data, security & more to compete in the Acceleration Economy!