Since TM project is consider as an external and for billing to customer
How about if internal projects are set up as TM, which is not going to be invoice. TM project cant be changed /revised to Internal project
What be the consequence and effect once TM Project which is so called internal project, its closed/finished and not invocied
please advise
Thanks and best regards
Ludwig Reinhard
Member
September 7, 2017 at 12:48 AM
?Hi, If you post transactions on a T&M project and do not invoice them, then you basically replicate an internal project. There is no negative effect or something that stops you from closing such a project. Best regards, Ludwig
—————————— Ludwig Reinhard SYCOR GmbH Goettingen —————————— ——————————————-
Sonya Oltmann
Member
September 7, 2017 at 1:17 AM
Also check to see how the TM project group is setup for costs and the GL…in our setup, if we don’t invoice a TM project, the costs (depending on line properties and categories) wouldn’t be expensed and would stay in our WIP account ‘waiting’ to be invoiced before moving to the expense accounts…
—————————— Sonya Oltmann RFI Enterprises, Inc. San Jose CA —————————— ——————————————-
Please note:
This action will also remove this member from your connections and send a report to the site admin.
Please allow a few minutes for this process to complete.
Report
You have already reported this .
Welcome to our new site!
Here you will find a wealth of information created for peopleĀ that are on a mission to redefine business models with cloud techinologies, AI, automation, low code / no code applications, data, security & more to compete in the Acceleration Economy!