I have a need where the Planning Worksheet should suggest a due date for Purchase Orders based on a Vendor Calendar.
I thought if I setup a Vendor Base Calendar and setup Non Delivery days to Nonworking that the system would plan for me.
The Scenario: I need to Produce an item 11/5 and it has a component on it that the vendor only delivers on Tuesday and Thursday.
I would like the due date of the item to consider the leadtime BUT also if that date is NOT a Tuesday or Thursday lets say roll back to the date priort.
Ā
Example
Production Order 11/5 CR09333
ItemĀ R-CR09333/34 5D LeadtimeĀ
Planning tells me due on 9/30 Which is a Friday but I want it to be Thursday 9/28 when they deliver
Ā
Help š
—————————— Jenn Claridge Sabre Limited Cambridge ON ——————————
When the plan is generated it plans for the date it is needed. When I carry out the action – it keeps the date and doesn’t update to the required days I would need.
Jenn
—————————— Jenn Claridge Sabre Limited Cambridge ON —————————— ——————————————-
Please note:
This action will also remove this member from your connections and send a report to the site admin.
Please allow a few minutes for this process to complete.
Report
You have already reported this .
Welcome to our new site!
Here you will find a wealth of information created for peopleĀ that are on a mission to redefine business models with cloud techinologies, AI, automation, low code / no code applications, data, security & more to compete in the Acceleration Economy!