Rescheduling jobs via Gantt Chart
-
Rescheduling jobs via Gantt Chart
Hello everyone!
When rescheduling a job for a specific production order via Gantt Chart, I will receive an error like below if it violates the job sequence:
Reference order number 2212000010. A job violates the job sequence. Job 20, 2, FVC01 is ending later than job 30, 2, JAT01 starts.
Is there any setup I can change to force Master Planning to reschedule the sequence operations as well when I’m rescheduling the current operation? I see there is an option to reschedule next operations in the Gantt Chart itself, but it will not reschedule operations with other resources.
Sorry, there were no replies found.
Log in to reply.