Are there any company’s using MS Project to Sync with a Project WBS in 2012 R3 successfully? We have Projects with up to 1000 lines and the MSP into AX has brought nothing but problems
1. On occasions the plans do not Sync 2. On occassions the planned dates and duractions move between the MSP plan and the Synchronised plan 3. Everything takes 3 times longer to action in MSP when it is connected to AX 4. Largest concern is that we are unable to Sync unless the user has System Admin access (we have been reporting this to Microsoft via our partners for 2 years without a solution!)
Surely we are not the only company in the world using this part of AX, lol…
PS: We are considering a move to 365, is the MSP functionality available for the Project Module in 365?
Many Thanks
—————————— Mac Young AAF Ltd Cramlington, UK ——————————
Please note:
This action will also remove this member from your connections and send a report to the site admin.
Please allow a few minutes for this process to complete.
Report
You have already reported this .
Welcome to our new site!
Here you will find a wealth of information created for peopleĀ that are on a mission to redefine business models with cloud techinologies, AI, automation, low code / no code applications, data, security & more to compete in the Acceleration Economy!