Reply To: Routing Scrap Factor?

  • Steven Chinsky MVP

    Member
    May 2, 2024 at 9:07 pm
    Up
    2
    Down
    ::

    @debpeters If you are looking to apply against components (Raw Materials) only, then I would use the Production BOM Scrap %. This way you are always pulling x% more than the stated Quantity per for the components. As for MRP, scrap % effects the expected quantity required for a Production Order and therefore is used in the planning engine. Your last statement about Standard Cost, if your Costing Method is Standard Cost and you have the Production BOM reflecting a Scrap%, when you rolled the Standard Cost the additional item cost will be included.

    Hope this helps.

    Steve