Storing Spec Sheets / Work instructions in D365FO

  • Storing Spec Sheets / Work instructions in D365FO

    Posted by DSC Communities on September 6, 2019 at 2:08 pm
    • Erik Fischer

      Member

      September 6, 2019 at 2:08 PM

      To all –

      I am looking to hear how anyone else using D365FO is managing production data beyond Item / BOM / Route information.Ā  We have several locations that also need Specification sheets, special work instructions, setup notes, etc for each production order that are in our legacy ERP solution but we have not found a great location to store this information in Dynamics.

      Can anyone provide some recommendations based on how they are doing it in D365 or is there some other ISV that may beĀ  better suited to manage this info?

      Thanks.?

      ——————————
      Erik Fischer
      ERP Program Manager
      HBD Industries
      Dublin OH
      ——————————

    • MICHAEL MILLS

      Member

      September 9, 2019 at 8:44 AM

      In many of the manufacturing companies I work with this is a requirement.Ā  We add specific attachments at the Route level and sometimes at the BOM and Item level.Ā  In the pass when the “traveler package” was generated which typically includes the picking list, route, QC documents, drawings andĀ  attachments were printed, are added to the traveler package. Ā  As computers on the shop floor increases I now have a lot of this information in the Job card.Ā  In the Job card I can have a picture of the subassembly or finish good, I can have work instructions and determine if they are monitory to be read, prior to starting the work, I can also attach pictures as part of work instructions, so if a weld needs to look a certain way I can show it in the work instructions.Ā  So my suggestion is take a look at the Job card functionally.

      ——————————
      Michael Mills
      AX D365 Enterprise Consultant Operations
      Blue Horseshoe Solutions
      Carmel, IN
      ——————————
      ——————————————-

    • Erik Fischer

      Member

      September 10, 2019 at 1:46 PM

      A follow up question –  what took it process have you seen at companies on how they produce the “traveler package”.?   Are there any ISV tools that can assist or is this Norte if a manual and custom process at each business.  I do not think a traveler package is something that is native to D365FO but I could be wrong.  Thoughts?

      ——Original Message——

      In many of the manufacturing companies I work with this is a requirement.Ā  We add specific attachments at the Route level and sometimes at the BOM and Item level.Ā  In the pass when the “traveler package” was generated which typically includes the picking list, route, QC documents, drawings andĀ  attachments were printed, are added to the traveler package. Ā  As computers on the shop floor increases I now have a lot of this information in the Job card.Ā  In the Job card I can have a picture of the subassembly or finish good, I can have work instructions and determine if they are monitory to be read, prior to starting the work, I can also attach pictures as part of work instructions, so if a weld needs to look a certain way I can show it in the work instructions.Ā  So my suggestion is take a look at the Job card functionally.

      ——————————
      Michael Mills
      AX D365 Enterprise Consultant Operations
      Blue Horseshoe Solutions
      Carmel, IN
      ——————————

    • Erik Fischer

      Member

      September 10, 2019 at 1:48 PM

      Follow up question. Can a job card ā€œproduceā€ the traveler package or does someone have to print each artifact manually?

      ——Original Message——

      In many of the manufacturing companies I work with this is a requirement.Ā  We add specific attachments at the Route level and sometimes at the BOM and Item level.Ā  In the pass when the “traveler package” was generated which typically includes the picking list, route, QC documents, drawings andĀ  attachments were printed, are added to the traveler package. Ā  As computers on the shop floor increases I now have a lot of this information in the Job card.Ā  In the Job card I can have a picture of the subassembly or finish good, I can have work instructions and determine if they are monitory to be read, prior to starting the work, I can also attach pictures as part of work instructions, so if a weld needs to look a certain way I can show it in the work instructions.Ā  So my suggestion is take a look at the Job card functionally.

      ——————————
      Michael Mills
      AX D365 Enterprise Consultant Operations
      Blue Horseshoe Solutions
      Carmel, IN
      ——————————

    DSC Communities replied 6 years, 9 months ago 1 Member · 0 Replies
  • 0 Replies

Sorry, there were no replies found.

The discussion ‘Storing Spec Sheets / Work instructions in D365FO’ is closed to new replies.

Start of Discussion
0 of 0 replies June 2018
Now

Welcome to our new site!

Here you will find a wealth of information created for peopleĀ  that are on a mission to redefine business models with cloud techinologies, AI, automation, low code / no code applications, data, security & more to compete in the Acceleration Economy!