Reply To: Validate the sequence operations in Production floor execution

  • Joseph Hurylovich

    Member
    November 28, 2024 at 3:05 pm
    Up
    1
    Down
    ::

    In production order default set up, there is a function called quantity validation. When properly configured, it allows a user to start an operation as long as an output quantity was produced from a previous operation. If no quantity was produced out of operation 10, operation 20 would not be allowed, to be started. I’m not in front of my laptop or I would point you to the section. Look into Production Quantity Validation.